Change order template
A change order template with the fields to fill in, sample wording for each, and a worked example showing how to price the extra work and the new timeline.

A change order is a short written record that the client has asked for something outside the agreed scope, what it costs and what happens to the schedule. It turns an awkward conversation into a routine one. This post gives you the fields, sample wording and a worked example.
This is general information, not legal advice. If your contracts are complex, have a professional review the terms that apply to changes.
When you need one
Raise a change order whenever a request would add cost, time or both, and was not in the signed scope. Common triggers:
- A new deliverable, such as three extra pages.
- A larger quantity of something already included.
- Rework after approval, when the original was built to the approved brief.
- A change in the date that you did not cause.
Small items you decide to absorb should still be recorded, as a goodwill note, so that the pattern is visible. Keeping the record is how you notice that a project has grown without a price attached.
The fields
- Reference. A number and the project name, for example "CO-01".
- Date and requester. When the request came in and who made it.
- Description of the change. What is being added, removed or altered, in plain words.
- Reason. Why it is needed, if known. Useful in review.
- Effect on scope. Which deliverables change.
- Effect on price. Hours, rate and total, shown as a calculation.
- Effect on timeline. New dates for affected milestones.
- Effect on other work. Dependencies, review rounds and anything pushed back.
- Approval. Name, date and a statement that the change is agreed.
- Validity. How long the quote holds, so that the price does not drift.
A worked example
Say the original project was 80 hours at $120 an hour.
- Original price: 80 x 120 = $9,600.
Midway through, the client asks for three extra landing pages. You estimate 12 hours.
- Change price: 12 x 120 = $1,440.
- New total: 9,600 + 1,440 = $11,040.
The timeline moves by three working days, because the pages are on the critical path for the launch. Say launch was set for Thursday 18 April. Three working days later is Tuesday 23 April: Friday, Monday, Tuesday.
Notice that the original price is not touched. The change is recorded separately, so you always know what the first agreement cost and what was added.
Sample wording
Use plain language. Short, specific and calm.
The message that opens it: "Thank you for the request. Adding three landing pages is outside the agreed scope, so I have written it up as a change order. It shows the extra cost and the effect on the launch date. Please read it and confirm if you would like to go ahead."
The description field: "Add three landing pages (campaign A, B and C) using the existing page layout. Copy to be supplied by the client."
The price field: "12 hours at $120 an hour = $1,440. Added to the original $9,600 for a revised total of $11,040."
The timeline field: "Launch moves from 18 April to 23 April. This assumes copy is received by 8 April."
The approval field: "By replying 'approved' or signing below, the client agrees to this change, its price and the revised timeline."
Handle the conversation
Keep the tone factual. Do not apologize for the document, and do not make the client feel accused. Say what you noticed and what you propose.
If the client disagrees about whether the item was in scope, return to the signed brief. The project brief template includes an out-of-scope field for this reason, and the new project setup checklist lists the change process as a step to define on day one.
Offer options when you can. "Option A: add the three pages for $1,440. Option B: add only the first page for 4 hours x $120 = $480 and decide on the others after launch." The client chooses with the numbers in front of them.
Be careful with the rate
If your hourly rate has increased since the original quote, say which rate applies to the change. Use the original rate for the original scope, and be explicit about the new one for new work. The effect of a rate change on a full year can be larger than it looks, as what a 10% rate increase does to your year shows.
Keep the log
Record every change order in one list: reference, date, description, value, status. Add them up at the end. If the total of approved changes is a large share of the original price, that tells you something about the quality of the original scope, and it belongs in your retrospective.
Changes that remove work
Not every change adds cost. A client may drop a deliverable. Treat that with the same discipline.
Say the client removes two pages that were estimated at 5 hours each, at $120 an hour.
- Removed hours: 2 x 5 = 10 hours.
- Value: 10 x 120 = $1,200.
Check whether any of that time has already been spent, and whether the removal frees capacity you can actually use. Work already done is billed. Write the credit and any amount retained into the same form, so the revised total is clear.
Next step
Create a one-page change order from the ten fields and save it with your project templates. Send the first one the next time a request makes you hesitate, even if the amount is small.
Keep reading
- Project brief templateA project brief template with ten fields, a prompt for each and a filled example, so the team and the client agree on goals, scope and success before work begins.
- New project setup checklistA checklist for starting a project, grouped into admin, team and client, with a short note on why each item matters and a rule for what must be done before work begins.
- Retainer scope templateA retainer scope template with ten fields and sample wording for hours, deliverables, rollover, response times and out-of-scope work. General information, not legal advice.
In HireOrSell
Ready to run it all in one place?
Projects, clients, time tracking and invoicing in one platform.