How often should you communicate with clients?
A communication cadence for each phase of a client project, from kickoff to launch to ongoing retainer, with a worked estimate of how many hours it takes.

There is no single correct number of messages per week. The right rhythm changes with the phase of the work, and the cost of getting it wrong runs in both directions. Too little contact leaves clients anxious. Too much eats your delivery hours. This post gives a cadence for each phase and shows how to estimate the time it takes.
Match the rhythm to the phase
Think of a project as five phases. Each has a different need.
- Kickoff: high contact, to build clarity.
- Build: steady and predictable contact, to keep trust without interrupting work.
- Review: more contact, because decisions are being made.
- Launch: concentrated contact, to handle the final details.
- Ongoing or retainer: a lighter and regular rhythm.
The rule across all phases is that clients should never have to wonder when they will next hear from you. Predictability matters more than volume.
Kickoff: about three touchpoints a week
In the first two weeks, expect to talk often. The tasks are collecting access, confirming scope and answering questions that block your work.
- A welcome message and kickoff call in the first days
- A written summary of decisions within one working day
- A short check-in midweek about outstanding items
Slow down after the first two weeks. The routine here overlaps with the client onboarding checklist for agencies, so use that list for the detail.
Build: one fixed update a week
While you work, send one written update on the same day each week. Keep it short: done, next, needs from you. Add a call only when decisions are required, not as a habit.
A fixed day does two things. It lets you plan your week around it, and it teaches the client not to chase. If you find clients still chase after a month, the update is probably unclear or the day keeps shifting.
Review: two touchpoints a week
During review phases the client has to make choices, and delays here hurt the schedule. Send the work with a clear request and a date. Follow up on the second working day if you have no reply. Book a short call to walk through feedback if there are several conflicting comments.
Remind clients of the agreed turnaround. The wording is in how to set client expectations in the first week.
Launch: near-daily until it is live
In the last week, near-daily contact is normal. A short message each morning with the plan for the day and each afternoon with what is done keeps nerves low. Confirm who is available on launch day and what the fallback plan is.
Ongoing: weekly or monthly, by value
For retainers, the pattern depends on how much changes. A brief written update every week works for active retainers. For quieter ones, a monthly summary and a quarterly call may be enough. Whatever you choose, keep it regular.
A worked example: counting the time
Say a 12-week website project follows this plan.
- Kickoff, weeks 1 and 2: 3 touchpoints per week = 3 x 2 = 6
- Build, weeks 3 to 9 (7 weeks): 1 update per week = 7
- Review, weeks 10 and 11: 2 per week = 2 x 2 = 4
- Launch, week 12: 4 touchpoints (near-daily) = 4
Total touchpoints: 6 + 7 + 4 + 4 = 21.
Assume each takes an average of 25 minutes including preparation. Then 21 x 25 = 525 minutes, and 525 / 60 = 8.75 hours.
That is the communication cost of the project, and it belongs in your price. At a $100 hourly rate it is 8.75 x 100 = $875. If your quote did not allow for it, the hours come out of your margin. These numbers are an example. Count your own for the next project.
Signs your cadence is wrong
- The client keeps asking for updates between your scheduled ones. Increase predictability, not frequency.
- Your updates repeat themselves. Move to a longer interval.
- You answer the same question three times. Put the answer in writing once and link to it.
- The client goes quiet in a phase that needs decisions. Raise it directly and set a date.
Fitting this around other work
Your own capacity is a limit as well. If you win new work and your calendar is full of ad hoc calls, the cadence collapses. Protect time for finding new work with a fixed routine, as described in how to find new local clients with a lead search routine. Both depend on the same habit: fixed slots, not whenever there is time.
Different people, different rhythms
Within one client, people want different things. A founder may want a two-line message weekly. A marketing manager may want the detail. A finance contact may only need invoice notices. Ask each person how they would like to hear from you, and write it into the client record.
Use shared channels with care. Adding everyone to every message creates noise, and people stop reading. Send the full update to the main contact and a short version to the rest, with a note on where to find more.
Next step
Write down your cadence for each of the five phases on one page. Share it with the next new client at kickoff, and note afterward whether they asked for more or less than you offered.
Keep reading
- How to find new local clients with a lead search routineA two-hour weekly routine to search for local prospects, qualify them quickly, make contact and log everything, with a worked example of the numbers it produces.
- How to set client expectations in the first weekSix expectations to state in the first week of a client engagement, each with sample wording you can adapt, plus a short written summary to send after the kickoff.
- How to follow up with leads without being pushyA five-touch follow-up cadence and ready-to-use scripts that add something useful each time, so you stay in view without nagging the people you want to work with.
In HireOrSell
Ready to run it all in one place?
Projects, clients, time tracking and invoicing in one platform.