Time tracking for web design agencies
How a web design agency can track time by design phase, count revisions, and log the handoff to development, with a worked 90-hour budget and an overrun example.

Web design projects rarely run over because the work is hard. They run over because revisions pile up, feedback arrives in pieces, and the handoff to development takes longer than anyone allowed for. This guide shows how to set up time tracking so those costs become visible, with a worked budget you can adapt.
Track by phase, not by project
One number for a whole project tells you nothing about where time went. Split every project into the same short list of phases so you can compare jobs.
A workable set for a design-led project:
- Discovery and brief
- Wireframes and structure
- Visual design
- Revisions
- Handoff to development
- Project management and client communication
Create these as tasks or milestones on every project. Keep the names identical across projects. After five or six jobs you will know how long each phase usually takes you, which makes the next quote better.
Build an hour budget from the price
Start from the price and your target rate, then divide the hours across the phases.
Say you agree a $9,000 fixed price for a ten-page marketing site, and your target rate is $100 per hour.
- Hours available: $9,000 / $100 = 90 hours.
- Discovery and brief: 10 hours.
- Wireframes and structure: 15 hours.
- Visual design: 30 hours.
- Revisions: 15 hours.
- Handoff to development: 10 hours.
- Project management and communication: 10 hours.
Check the total: 10 + 15 + 30 + 15 + 10 + 10 = 90 hours. The budget matches.
Now the project runs. Visual design comes in at 30 hours, as planned. Revisions take 24 hours because the client asked for a third round. Handoff takes 12. The others stay on budget.
Actual total = 10 + 15 + 30 + 24 + 12 + 10 = 101 hours. Effective rate = $9,000 / 101 = about $89.11 per hour. The revisions line alone, 24 against 15, accounts for 9 of the 11 extra hours.
Treat revisions as their own line
Revisions are a common source of drift in design work, so give them a separate task and an agreed allowance.
- State in the proposal how many rounds are included, for example two.
- Define a round: one consolidated set of feedback from the client, not a series of emails.
- Log every revision hour to the revisions task, even if it is small.
- When the allowance is reached, say so before starting the next round.
With the allowance in the contract and the hours visible, the conversation about a third round is about a number, not a feeling. In the example, a third round at your rate would cost 9 hours x $100 = $900, which you can quote in advance.
Log the handoff separately
Handoff to development is where design time can hide. Preparing assets, writing notes, answering developer questions and reviewing the build against the design all take hours, and they happen after the design looks finished.
Create a handoff task with sub-items:
- Exporting assets and specifying styles.
- Walkthrough with the developer.
- Answering questions during the build.
- Design review of the built pages.
If the developer is on your team, track their hours on the same project so you see the full cost of the site. If they are an outside contractor, log your own hours to the handoff task and compare them with the budget.
Make logging easy
Time tracking fails when it is a chore. A few habits help:
- Log at the end of each work block, not at the end of the week.
- Use the phase names, not free text, so reports can be grouped.
- Mark each entry billable or non-billable. Internal critique and rework from your own mistakes belong in non-billable.
- Review the phase totals every Friday for ten minutes, against the budget above.
Setting it up in HireOrSell
HireOrSell supports time against projects and milestones, billable and non-billable marking, project budget tracking and Gantt charts, so phases can be set up as milestones and compared with the plan. The Free plan does not include time tracking; Pro is $5 per seat per month and includes full time tracking. Check the pricing page for current prices. If you are comparing several tools first, best time tracking software for agencies: nine tools compared sets them side by side.
After the project
Spend fifteen minutes on a review: planned and actual hours per phase, and the effective rate. Write down the one phase that moved the most and why. Use the figures to adjust your phase percentages for the next quote. In the example, revisions were planned at 15 of 90 hours, or 16.7%, and ran at 24 of 101, or 23.8%. That gap is the first thing to change.
Three traps to watch for
- Feedback in pieces. Five emails of comments over a week cost more than one meeting. Ask for a single consolidated list, and log the time spent reading and replying to extra messages under communication.
- Untracked small fixes. A quick tweak of fifteen minutes feels too small to log. Ten of them in a week is 2.5 hours, or $250 at $100 per hour. Log them anyway.
- Rounding up the budget after the fact. If you adjust the plan whenever actuals drift, the comparison tells you nothing. Keep the original budget fixed and record changes as separate lines.
Next step
Choose your current design project and split its hours into the six phases above. Set a budget for each from the price. Log hours against the phases for one week and see which line moves first.