A time audit is a short, deliberate experiment: for five working days, everyone records where their time goes in more detail than usual, and then you look at the result. It tells you what your normal tracking misses. The plan below gives you a task for each day and five questions to ask once the week is over.

Before Monday: set it up

Choose a normal week, not one with a holiday or a launch. Tell the team why you are doing it and what you will not do with the data: it is to find process problems, not to rank people.

Agree on a short list of categories so everyone logs the same way. A workable set:

  • Client work, by client and project.
  • Meetings, split into client and internal.
  • Sales and proposals.
  • Admin and finance.
  • Rework and fixes.
  • Learning and other.

Ask everyone to log in blocks of 15 minutes or more, with a one-line note. Decide where to log, and make sure it is open on everyone's screen on Monday morning.

Monday: start and calibrate

Everyone logs from the start of the day. At 4 pm, hold a five minute check: is the list of categories working, and is anything unclear? Fix the categories now, not on Friday.

Remind people that rough is fine. A log that is 90 percent accurate is far more useful than one that is perfect and abandoned.

Tuesday: log as you go

Nothing to change, only to keep going. If you use a timer, watch for timers left running overnight or through lunch. For the habits that help here, see the post on time tracking habits that stick on a small team.

Wednesday: midweek review

Spend 15 minutes looking at the first two days. Check three things: are there gaps in anyone's day, are there entries labelled "other" with no notes, and are any entries suspiciously round or long? Ask people to fill gaps today while they can still remember.

Thursday: capture the interruptions

Add one extra instruction: when you are interrupted, note it. A simple tally is enough, with a mark for each time someone switches task because of a message or a request. Interruptions rarely appear in time logs, but they affect how much real work fits into a day.

Friday: finish and total

Everyone completes their log by mid-afternoon. Total the hours by person and by category. Then hold the review meeting, with the five questions below.

The totals: a worked example

Say a four-person team has a capacity of 4 x 40 = 160 hours for the week. The audit shows 138 hours logged. The gap is 160 - 138 = 22 hours, and 22 / 160 = 0.1375, or 13.75 percent of capacity unaccounted for.

Of the 138 logged hours, 96 are client work. The share is 96 / 138 = 0.6957, or 69.6 percent.

These numbers are illustrative. A gap of 22 hours could be breaks, travel, or work that nobody recorded. The audit does not tell you which, but it tells you the size of the question.

Five questions to ask the results

  1. Where is the gap? Compare logged hours with hours worked. Which people or days have the largest difference, and what was happening on those days?
  2. What took longer than quoted? For each active project, compare hours logged with the estimate. Note the tasks that ran over, and the reason.
  3. What was never billable? List the non-billable categories in order of hours. Decide which are essential and which could shrink. The post on billable versus non-billable time gives a decision list for borderline cases.
  4. Where did time leak? Check meetings, rework and small tasks for hours that should have been charged. The list of seven places billable hours go missing is a useful checklist to read next to the totals.
  5. What does this change? Pick one estimate, one process and one habit that will be different next week.

Turn the findings into estimates

The most direct use of the audit is better estimating. If a type of task took 11 hours when you quoted 8, the next quote should reflect it. The post on how to estimate project hours without guessing shows how to use real hours from past work as the basis.

Reading the week by person and by client

After the totals, cut the data two ways. First, by person: do hours per category look similar across the team, or does one person carry most of the meetings and another most of the admin? A lopsided pattern is a prompt to rebalance work, not a verdict on anyone.

Second, by client: list the hours for each client and compare them with the revenue that client brings. In the example above, if one client used 30 of the 96 client hours, that is 30 / 96 = 0.3125, or 31.25 percent of client time. Ask whether that client also brings about a third of your revenue. If not, you have found a place to look more closely.

One week will not settle that question, but it tells you where to start.

Pitfalls

  • Changing the work to look good. If people know they are being measured, they may behave differently for a week. Repeat the audit after a month if the result looks too tidy.
  • Treating one week as truth. One week is a sample. Look for patterns that match what you already suspected, and treat surprises as questions.
  • Ending with a report and no change. Choose one action from the review and name an owner.

Next step

Book next week in your calendar as the audit week and send the category list to your team today. Hold the Friday review before you leave on Friday, while the week is fresh.

Free plan available

Ready to run it all in one place?

Projects, clients, time tracking and invoicing in one platform.